Gegensteuerungsphase
Gegensteuerungsphase refers to a critical period in project management, particularly within the PRINCE2 methodology. It is a phase that occurs when a project is identified as deviating significantly from its planned baseline, whether in terms of time, cost, quality, scope, risk, or benefits. The core purpose of the Gegensteuerungsphase is to address these deviations and bring the project back under control.
During this phase, the project manager is responsible for analyzing the extent of the deviation and identifying
The Gegensteuerungsphase is initiated by an Exception Report, which formally alerts the Project Board to the