PERTDiagramme
PERT diagram, short for Program Evaluation and Review Technique, is a project management tool used to plan and schedule complex projects by focusing on time and uncertainty. It represents a project as a network of activities and milestones, helping managers identify the sequence of tasks, parallel work, and the critical path where delays directly affect the project end date. PERT diagrams can be drawn in two common forms: activity-on-node (AON) and activity-on-arrow (AOA), allowing flexibility in how activities and dependencies are depicted.
A hallmark of PERT is the use of probabilistic time estimates. For each activity, three time estimates
How PERT is used: identify activities and dependencies, estimate time with three-point data, construct the network,
Limitations include the reliance on accurate time estimates and the potential complexity for large projects; PERT