PERTanalüüs, short for Program Evaluation and Review Technique analysis, is a project management technique used to estimate project duration and identify critical tasks. It is particularly useful for projects with a high degree of uncertainty in task durations. PERT analysis involves breaking down a project into individual tasks and then estimating the time required for each task.
Instead of a single-point estimate, PERT uses three time estimates for each task: optimistic, most likely, and
The PERT technique also involves identifying the critical path, which is the sequence of tasks that determines
PERT analysis helps in understanding project risks by providing a probabilistic approach to time estimation. It