finishtofinish
Finish-to-finish (FF) is a dependency type used in project management and scheduling. It links two activities such that the completion of the successor is constrained by the completion of the predecessor. The two activities may start at different times, and a lag can be specified to adjust their alignment.
With a finish-to-finish relationship, the successor cannot finish before the predecessor finishes; if the predecessor finishes
Practically, FF is useful when a deliverable cannot be considered complete until another deliverable has also
FF is one of the four basic dependency types in traditional CPM/PERT terminology; the others are finish-to-start,