Starttostart
Start-to-Start (SS) is a type of logical relationship in project scheduling in which the start of one task (the successor) depends on the start of another task (the predecessor). In an SS link, the earliest possible start of the successor cannot occur before the predecessor has started. The relation may include a lag or, less commonly, a lead time, which shifts the timing relative to the predecessor’s start. SS is one of the traditional dependency types used in CPM and PERT, alongside Finish-to-Start, Finish-to-Finish, and Start-to-Finish.
In practice, SS is used to coordinate tasks that should begin together or when the start of
Example: Task A represents site preparation and Task B represents foundation work that should begin around
Usage and implications: SS helps model parallel or coordinated starts but can complicate schedule calculations and